Archive for September, 2007

The Avenue District Hard Hat Tour

Friday, September 28th, 2007

A top-to-bottom look at The Avenue District
On Saturday, Sept. 22, 2007, Zaremba hosted The Avenue District Hard Hat Tour for future residents of the walkable neighborhood.
The day started out at 9 a.m. with continental breakfast, and then participants split into two groups – one lead by Matt Zaremba and Site 3 project manager Mike Sathre, [...]

Trend Tracker Links (9.24.07)

Monday, September 24th, 2007

Urban Model for the NationWashington Post - United StatesBy Alejandro Lazo“Christopher B. Leinberger, a visiting fellow with the Brookings Institution, believes the move into urban corridors that is occurring in …”
University Circle developers announce a high quality short list of … Plain Dealer – Cleveland, OH“A bird’s eye view shows the general massing of the [...]

1211 St. Clair Ave. - 2nd Floor Construction Video

Saturday, September 22nd, 2007

Work has progressed to the 2nd floor at 1211 St. Clair Ave. Check out the brief video below taken on Friday, Sept. 21.

The 10-story building, at the intersection of East 12th Street and St. Clair Avenue in downtown Cleveland, will include 50 elegant lofts (floors 3-8), eight penthouses (floors 9-10) and up to 9,000 square [...]

Ground-Level Images from Site 1 - Sept. 12

Thursday, September 13th, 2007

Photos taken from East 12th Street on Sept. 12, 2007 show progress on 1211 St. Clair, future home to 50 elegant lofts, eight penthouses and up to 9,000 square feet of retail space in The Avenue District, downtown Cleveland’s premier walkable neighborhood.

Avenue District Townhome Images - Sept. 12

Thursday, September 13th, 2007

Masonry work continues on the first 10 townhomes in The Avenue District. The rubber roof is now complete, and installation of the rooftop decks is underway.
The plumbing and electric roughs (behind the walls) are completed in most units, with insulation and drywall beginning in select units later this month. Buyers will also finish their [...]

Masonry Works Begins on Site 3 Townhomes

Thursday, September 6th, 2007

Masonry work is underway on Site 3 townhomes at The Avenue District, located at Rockwell Avenue and the newly created East 15th Street in downtown Cleveland.
In addition to the masonry skin, the rubber roof is now complete, with installation of the rooftop decks starting later this week. The plumbing and electric roughs (behind the walls) [...]

Images from Site 1 - Aug. 31

Saturday, September 1st, 2007

In the late-afternoon shadows of downtown Cleveland’s skyline, The Avenue District’s Building One rises at East 12th Street and St. Clair Avenue:
The tower crane stands 254 feet above Site 1 at The Avenue District: